Project HIghlights

  • $21.4M Construction Cost
  • Completed 2016
  • 400-Acre Hillside Grading
    • 2,600,000 cubic yards of engineered fill
    • 2,000,000 cubic yards of buttress excavation & backfill
  • Drainage Design
  • Advertisement and Bid Support
  • Construction Staking
  • Consultant Coordination

Project Description

CNC Engineering provided survey, design and construction services for the mass grading a portion of a 400-acre hillside area, west of Grand Avenue, north of the Pomona Freeway, removing approximately 2,600,000 cubic yards of uncompacted soil and placing it as engineered fill and approximately 2,000,000 cubic yards of buttress excavation and backfill. The project also includes storm drains, bench drains, down drains, detention basin, curb & gutter, paving, irrigation, and landscaping.