Avenida Vaquero Pavement Rehabilitation

City of San Clemente

 Highlights:

– Land Survey
– Utilities
– ADA Compliance
– Horizontal Control

CNC Engineering provided plans, specifications and estimates for resurfacing and reconstruction of Avenida Vaquero in the city of San Clemente. Work involved preparation of base maps, field survey, re-establishing the horizontal alignment, utilities, geotechnical investigation and pavement alternative studies, cement treated base, design of a new street profile to meet standard cross slope required by the City, removal and replacement of curb and gutter and sidewalks, ADA access ramps, cross gutter, striping and traffic loop replacement. CNC also prepared final as-built record drawings for this project and submitted all final documents to the City.